Full planning application for the erection of 9 residential units with access and parking provision
The map marker may not show the precise location of the application. Map locations are, where possible, taken from the official coordinates of the relevant Unique Property Reference Number (UPRN), as published in the OS OpenUPRN database. In some cases, particularly where there is a planning application on open land not linked to an existing property, they may be estimated from the location description or taken from the OS coordinates given in the planning application.
View this application at the Wychavon Planning Portal
Description: Full planning application for the erection of 9 residential units with access and parking provision
Status: Approval
Applicant Name
T+S Properties LTD
Application Location
Evesham Marina
Kings Road
Evesham
UPRN
Ward
Bengeworth Ward - Pre 01/05/23
Parish
Evesham
Agent Name
Zesta Planning Ltd
Agent Address
The Site
Chosen View Road
Cheltenham
GL51 9LT
Application Reference: W/22/01557/FUL
Application Type: Full planning permission
Case Officer: Leanne Pogson
Decision Level: Committee
Application Received Date: Tuesday 12 July 2022
Application Valid Date: Wednesday 24 August 2022
Consultation Start Date: Thursday 25 August 2022
Consultation End Date: Friday 14 October 2022
Site Visit Notice Date: N/A
Advert Expiry Date: N/A
Committee Date: Thursday 10 November 2022
Decision Date: Monday 28 November 2022
Appeal Date: N/A
Appeal Decision: N/A
Application documents are not linked directly from this website. To download and view documents, please visit the Wychavon Planning Portal.
The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents – 001C, 101D, 102D, 103, 104, 105, F106, F107, F108, 109, 901B, 903 and 904C, 906, 112, 113. Reason: To define the permission.
No development above floor slab level shall take place until details of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted to and approved in writing by the local planning authority. The details to be submitted shall include:-
- trade description and/or samples of external brickwork, roofing and cill and lintel materials.
The development shall be carried out using the materials as approved.
Reason - To ensure that the new materials are in keeping with the surroundings and/or represent quality design in accordance with policy SWDP21 of the South Worcestershire Development Plan.
The development hereby approved shall not be occupied until the access road, parking and turning facilities have been provided in accordance with Drawing No. 102D.
Reason: To conform with the submitted details.
The development hereby approved shall not be brought into use until 9 electric vehicle charging spaces have been provided in accordance with a specification which shall be submitted to and approved by the Local Planning Authority and thereafter such spaces and power points shall be kept available and maintained for the use of electric vehicles as approved.
Reason: To encourage sustainable travel and healthy communities.
The development hereby permitted shall not be first occupied until sheltered and secure cycle parking to comply with the Council’s adopted highway design guide has been provided in accordance with details as shown on drawing numbers 101D, 112 and 113 and thereafter the approved cycle parking shall be kept available for the parking of bicycles only.
Reason: To comply with the Council’s parking standards
No development shall take place, including any works of demolition, until a Construction Environment Management Plan - Statement has been submitted to and approved in writing by the Local Planning Authority. The statement shall provide for:
a) the parking of vehicles of site operatives and visitors;
b) loading and unloading of plant and materials;
c) storage of plant and materials used in constructing the development;
d) details of the routing of HGV,s and delivery lorries on the highway network
associated with the proposed development to and from the site together with
agreed traffic management measures
e) responsible persons and lines of communication
f) measures to control the emission of dust and dirt during construction;
h) delivery, demolition and construction working hours.
The approved construction method statement shall be adhered to throughout the construction period for the development.
approved. Site operatives' parking, material storage and the positioning of operatives' facilities shall only take place on the site in locations approved in writing by the Local Planning Authority.
The CEMP should generally comply with the requirements of Worcestershire Regulatory Services Code of Best Practice for Demolition and Construction Sites 2nd Edition September 2020 and the Construction Logistics and Community Safety (CLOCS) Standard www.clocs.org.uk/clocsworks
Reason: To protect existing and new occupiers of residential areas from the unreasonable effects of noise, vibration, light and dust nuisance, to avoid and mitigate for any potential impact on protected species, minimise the risk of accidents and ensure public rights of way are kept available where possible for the duration of the construction, in accordance with Policies SWDP4, 21 and 22 of the South Worcestershire Development Plan.
Unless otherwise agreed by the Local Planning Authority development, other than that required to be carried out as part of an approved scheme of remediation, must not commence until conditions 1 to 6 have been complied with:
1. A preliminary risk assessment must be carried out. This study shall take the form of a Phase I desk study and site walkover and shall include the identification of previous site uses, potential contaminants that might reasonably be expected given those uses and any other relevant information. The preliminary risk assessment report shall contain a diagrammatical representation (conceptual model) based on the information above and shall include all potential contaminants, sources and receptors to determine whether a site investigation is required and this should be detailed in a report supplied to the Local Planning Authority. The risk assessment must be approved in writing before any development takes place.
2. Where an unacceptable risk is identified a scheme for detailed site investigation must be submitted to and approved in writing by the Local Planning Authority prior to being undertaken. The scheme must be designed to assess the nature and extent of any contamination and must be led by the findings of the preliminary risk assessment. The investigation and risk assessment scheme must be compiled by competent persons and must be designed in accordance with the Environment Agency's "Land Contamination: Risk Management" guidance.
3. Detailed site investigation and risk assessment must be undertaken and a written report of the findings produced. This report must be approved by the Local Planning Authority prior to any development taking place. The investigation and risk assessment must be undertaken by competent persons and must be conducted in accordance with the Environment Agency's "Land Contamination: Risk Management" guidance.
4. Where identified as necessary a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and is subject to the approval of the Local Planning Authority in advance of undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in relation to the intended use of the land after remediation.
5. The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development, other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority.
6. Following the completion of the measures identified in the approved remediation scheme a validation report that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval of the Local Planning Authority prior to the occupation of any buildings.
7. In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken and where necessary a remediation scheme must be prepared, these will be subject to the approval of the Local Planning Authority. Following the completion of any measures identified in the approved remediation scheme a validation report must be prepared, which is subject to the approval in writing of the Local Planning Authority prior to the occupation of any buildings.
Reason: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy SWDP 31 of the South Worcestershire Development Plan.
Prior to installation, details of renewable and/or low carbon energy generation measures shall be submitted to and approved in writing by the Local Planning Authority. The measures shall contribute to at least 10% of the predicted energy requirements of the development. The details to be submitted shall include:- - the overall predicted energy requirements of the approved development; - the predicted energy generation from the proposed renewable/low carbon energy measures; and - an implementation timetable for the proposed measures. The development shall be carried out in accordance with the approved details. Reason - To ensure the development supports the delivery of low carbon/renewable energy and safeguards natural resources in accordance with policy SWDP27 of the South Worcestershire Development Plan.
The development hereby permitted shall not be occupied until full details of all foul and surface water drainage systems to serve the development have been submitted to and approved in writing by the Local Planning Authority. The approved drainage works shall be implemented in accordance with the approved details before the first occupation/use of the development hereby permitted and shall be retained thereafter. Reason: To ensure development would not result in unacceptable risk of pollution or harm to the environment and to ensure the proposed development does not exacerbate flood risk and deals with surface water run-off from the site in a sustainable manner, in accordance with policies SWDP28, SWDP29 and SWDP 30 of the South Worcestershire Development Plan.
Before the first occupation of the development hereby permitted a plan indicating the positions, design, materials and type of boundary treatment to be erected shall be submitted to and approved in writing by the local planning authority The boundary treatment shall be completed before the first occupation of the development hereby permitted. Development shall be carried out in accordance with the approved details. Reason - To protect the amenities of properties and ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan..
Prior to the first use/occupation of the development hereby permitted, the details set out in the submitted Water Management Statement shall be fully implemented and remain thereafter. Reason: To ensure that an appropriate sustainable drainage system is provided to serve the development in accordance with policy SWDP29 of the South Worcestershire Development Plan 2016.
Prior to the first occupation of any of the dwellings hereby approved, details of superfast broadband facilities or alternative solutions to serve the dwellings hereby approved shall be submitted to and approved in writing by the local planning authority. The submitted details shall include an implementation programme. The facilities shall be provided in accordance with the approved details.
Reason: To ensure the proposal incorporates satisfactory telecommunication facilities in line with policy SWDP26 of the South Worcestershire Development Plan 2016.
Notwithstanding the details shown on the Landscape Plan, DWG No. 904C, before the first occupation of the development hereby permitted a scheme of landscaping shall be submitted to and approved in writing by the Local Planning Authority. The landscaping scheme shall include:- (i) a plan(s) showing details of all existing trees and hedges on the application site. The plan should include, for each tree/hedge, the accurate position, canopy spread and species, together with an indication of any proposals for felling/pruning and any proposed changes in ground level, or other works to be carried out, within the canopy spread. (ii) a plan(s) showing the layout of proposed tree, hedge and shrub planting and grass areas. (iii) a schedule of proposed planting - indicating species, sizes at time of planting and numbers/densities of plants. (iv) a written specification outlining cultivation and other operations associated with plant and grass establishment. (v) a schedule of maintenance, including watering and the control of competitive weed growth, for a minimum period of five years from first planting. All planting and seeding/turfing shall be carried out in accordance with the approved details in the first planting and seeding/turfing seasons following the completion or first occupation/use of the development, whichever is the sooner. The planting shall be maintained in accordance with the approved schedule of maintenance. Any trees or plants which, within a period of five years from the completion of the planting, die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species. Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan.
Before the first occupation of the development hereby permitted a schedule of landscape maintenance for a minimum period of 10 years has been submitted to and approved in writing by the local planning authority. The schedule shall include details of the arrangements for its implementation, long-term design objectives, management responsibilities and maintenance schedules for all landscape areas (excluding domestic gardens). The approved landscape maintenance schedule shall be fully implemented. Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan.
The development hereby permitted shall be carried out in strict accordance with the biodiversity enhancement measures as shown on the Landscape Plan, DWG No. 904C and submitted with this application and retained thereafter.
Reason: To ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDP22 of the South Worcestershire Development Plan.
Positive and Proactive Statement. No problems have arisen in dealing with this application. The planning application sought an acceptable form of development consistent with the requirements of relevant policies and material considerations. No amendments or alterations were therefore required and no further positive or proactive action was deemed necessary.
W/25/01209/CCO
Evesham Marina, Kings Road, Evesham
Discharge of Conditions 8 Parts 1-3 (Contaminated Land Risk Assessment), 14 (Soft Landscaping Scheme) and 15 (Landscape Maintenance Plan) of Planning Permission number W/22/01557/FUL
Added Friday 6 June 2025
Decision: Approval
Decided Monday 4 August 2025
There are no other planning applications within 100m of this property