Development of a 2,973 sqm building for uses classes E(g)(iii) (Light Industrial Use), B2 (General Industrial) and B8 (Storage and Distribution) and Associated Infrastructure as approved under planning reference W/22/01420/FUL - variation of conditions 10 and 11.
The map marker may not show the precise location of the application. Map locations are, where possible, taken from the official coordinates of the relevant Unique Property Reference Number (UPRN), as published in the OS OpenUPRN database. In some cases, particularly where there is a planning application on open land not linked to an existing property, they may be estimated from the location description or taken from the OS coordinates given in the planning application.
View this application at the Wychavon Planning Portal
Description: Development of a 2,973 sqm building for uses classes E(g)(iii) (Light Industrial Use), B2 (General Industrial) and B8 (Storage and Distribution) and Associated Infrastructure as approved under planning reference W/22/01420/FUL - variation of conditions 10 and 11.
Status: Approval
Applicant Name
Paul O'Neill, Nevache Limited
Application Location
Plot 700
Blenheim Drive
Vale Park
Evesham
UPRN
Ward
Elmley Castle and Somerville Ward - Pre 01/05/23, Little Hampton Ward - Pre 01/05/23, Evesham South
Parish
Evesham, Hinton on the Green
Agent Name
Mr Ed Simcox, Harris Lamb Ltd
Agent Address
75-76 Francis Road
Birmignham
B16 8SP
Application Reference: W/23/00760/FUL
Application Type: Full planning permission
Case Officer: Emma Ridley
Decision Level: Delegated
Application Received Date: Thursday 13 April 2023
Application Valid Date: Thursday 13 April 2023
Consultation Start Date: Monday 24 April 2023
Consultation End Date: Monday 3 July 2023
Site Visit Notice Date: N/A
Advert Expiry Date: Friday 26 May 2023
Committee Date: N/A
Decision Date: Tuesday 11 July 2023
Appeal Date: N/A
Appeal Decision: N/A
Application documents are not linked directly from this website. To download and view documents, please visit the Wychavon Planning Portal.
The development hereby permitted must be commenced not later than the expiration of three years from the date of the original permission 22/01420/FUL dated 7/2/23. Reason: To conform with the requirements of Sections 73 and 91 of the Town and Country Planning Act 1990 (as amended).
Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents –
Dr. numbers:-
Site location Plan
Site location, plan 023 Rev B
7059/017 Rev B Elevations
018 Rev A Elevations.
013 Floor Plan
019 Rev A section
024 Rev B Proposed site plan
025 Rev B Proposed Plot Plan
026 Rev B proposed, plot plan
22-361-SK00004 P3 Proposed Sections and Flood Compensation Strategy
The Planting plan VPE PP1 Rev B
Ecological Mitigation and Enhancement Strategy, Rev.B, by Focus Ecology dated June 2023.
Reason: To define the permission.
The Development hereby approved shall not be brought into use until the access, parking and turning facilities have been provided as shown on drawing 7059-023 Revision B. Reason: To ensure conformity with submitted details.
The Development hereby approved shall not be brought into use until the applicant has implemented the Travel Plan using Modeshift STARS Business format as submitted. The development hereby approved must meet green level accreditation before occupation and bronze level accreditation within 12 months of occupation.
Reason: To reduce vehicle movements and promote sustainable access in accordance with policy SWDP4 of the adopted South Worcestershire Development Plan.
Before the completion of development hereby permitted, details of renewable and/or low carbon energy generation measures as outlined in the submitted ESC Energy Statement (June 2022) shall be carried out on site .The measures shall contribute to at least 10% of the predicted energy requirements of the development and the building shall not be occupied until these measures are operational.
Reason - To ensure the development supports the delivery of low carbon/renewable energy and safeguards natural resources in accordance with policy SWDP27 of the South Worcestershire Development Plan.
Before the first use/occupation of the development hereby permitted a scheme of landscaping shall be submitted to and approved in writing by the Local Planning Authority. The landscaping scheme shall include:- (i) a plan(s) showing details of all existing trees and hedges on the application site. The plan should include, for each tree/hedge, the accurate position, canopy spread and species, together with an indication of any proposals for felling/pruning and any proposed changes in ground level, or other works to be carried out, within the canopy spread. (ii) a plan(s) showing the layout of proposed tree, hedge and shrub planting and grass areas. (iii) a schedule of proposed planting - indicating species, sizes at time of planting and numbers/densities of plants. (iv) a written specification outlining cultivation and other operations associated with plant and grass establishment. (v) a schedule of maintenance, including watering and the control of competitive weed growth, for a minimum period of five years from first planting. All planting and seeding/turfing shall be carried out in accordance with the approved details in the first planting and seeding/turfing seasons following the completion or first occupation/use of the development, whichever is the sooner. The planting shall be maintained in accordance with the approved schedule of maintenance. Any trees or plants which, within a period of five years from the completion of the planting, die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species. Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan.
Prior to the first use/occupation of the development hereby permitted, the details set out in the submitted Water Management Statement which is found in the Flood Risk Assessment submitted with the application shall be fully implemented and remain thereafter.
Reason: To ensure that an appropriate sustainable drainage system is provided to serve the development in accordance with policy SWDP29 of the South Worcestershire Development Plan 2016.
Prior to its construction as part of this development hereby approved details of the wall as shown on dr. no. 22-361-SK00004 P3 to be erected to the perimeter of the northern and eastern part of the site shall be first submitted to and approved in writing with the Local Planning Authority. The development shall be constructed in accordance with those details.
Reason: In the interests of the ecological retention and enhancement of the area in accordance with policy SWDP22 of the SWDP.
The development hereby permitted shall be carried out in strict accordance with the recommendations set out in the para 8.2.2 of the Ecological Mitigation and Enhancement Strategy, ref.2509 Rev.01, by Focus Ecology dated May 2022 submitted with this application. In particular: - bat and bird boxes, log piles and hedgehog houses.
Reason: To ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDP22 of the South Worcestershire Development Plan.
The development must be undertaken in accordance with the approved Ecological Enhancement Strategy document (PE0364) dated June 2023. The biodiversity net-gain scheme identified shall be undertaken prior to the development hereby permitted being brought into first use or otherwise occupied in accordance with the approved details and timetable.
Reason: To ensure that the proposed development contributes to the conservation and enhancement of biodiversity within the site and for the wider area in accordance with SWDP 22.
The development must be implemented in accordance with the Ecological Enhancement Strategy document (PE0364) June 2023. A report describing the results of monitoring shall be submitted to the local planning authority at intervals identified in the LEMP strategy. The plan and monitoring report shall also set out where the results of the monitoring to show if conservation aims and objectives of the LEMP are not being met, how contingencies and/or remedial action will be identified if the aims are not met, and agreed and implemented so that the development still delivers the fully functioning biodiversity objectives of the originally approved scheme. The approved plan will be implemented in accordance with the approved details.
Reason: To ensure that the proposed development contributes to the conservation and enhancement of biodiversity within the site and for the wider area in accordance with SWDP 22.
Before the development hereby permitted is first occupied/used, details of any external lighting to be provided in association with the development shall be submitted to and approved in writing by the Local Planning Authority. The details shall include times when the external lighting will not be switched on. Only external lighting in accordance with approved details shall be provided on the application site. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order with or without modification) there shall be no other external lighting provided on the application site. Reason: To ensure that lighting is directed away from the vegetated corridors and that the brook is kept as dark as possible and to ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDP22 of the South Worcestershire Development Plan.
Positive and Proactive Statement. In dealing with this application, the Council has worked with the applicant in the following ways:- seeking further information following receipt of the application; seeking amendments to the proposed development following receipt of the application; - considering the imposition of conditions and or the completion of a s.106 legal agreement. In such ways the Council has demonstrated a positive and proactive manner in seeking solutions to problems arising in relation to the planning application.
W/24/02411/CCO
Plot 700, Blenheim Drive, Vale Park, Evesham
Discharge of condition 8 (approved wall details) and 12 (external lighting) of planning permission reference W/24/00471/FUL
Added Monday 16 December 2024
Decision: Approval
Decided Friday 30 January 2026
W/24/00471/FUL
Plot 700, Blenheim Drive, Vale Park, Evesham
Variation of condition 2 of permission reference W/23/00760/FUL (Development of a 2,973 sqm building for uses classes E(g)(iii) (Light Industrial Use), B2 (General Industrial) and B8 (Storage and Distribution) and Associated Infrastructure as approved under planning reference W/22/01420/FUL - variation of conditions 10 and 11)
Added Thursday 14 March 2024
Decision: Approval
Decided Thursday 20 June 2024
W/24/00073/NMA
Plot 700, Blenheim Drive, Vale Park, Evesham
Non-material amendment to application reference W/23/00760/FUL for Development of a 2,973 sqm building for uses classes E(g)(iii) (Light Industrial Use), B2 (General Industrial) and B8 (Storage and Distribution) and Associated Infrastructure as approved under planning reference W/22/01420/FUL - variation of conditions 10 and 11 - relocation of roller shutter doors and fire doors; change of finish to fire doors; addition of two flues; inclusion of vertical rise sectioned overhead door; alterations to design of entrance canopy, changes to colour of doors, rainwater goods and windows; addition of solar panels; replace concrete panels with composite wall panel cladding.
Added Monday 15 January 2024
Decision: Refusal
Decided Tuesday 6 February 2024
W/22/01420/FUL
Plot 700, Blenheim Drive, Vale Park, Evesham
Development of a 2,973 sqm building for uses classes E(g)(iii) (Light Industrial Use), B2 (General Industrial) and B8 (Storage and Distribution) and Associated Infrastructure
Added Tuesday 19 July 2022
Decision: Approval
Decided Thursday 9 February 2023
There are no other planning applications within 100m of this property