Scheduled work by Openreach from Sunday 7 June 2026 to Wednesday 10 June 2026
Marker may not indicate precise location of the roadworks.
Description: Excavation on the F/P Verge to Install a New
BT Duct from F/P Verge Chamber to End Customer to provide new fibre service. 22Mtrs F/P Verge Duct.
Start: Sunday 7 June 2026 23:00
Finish: Wednesday 10 June 2026 00:00
Start and finish times are subject to change
Location: Harvard Avenue
Traffic management: No carriageway incursion
Effect on traffic: Delays unlikely
Effect on footway: Provide Alternative Route
Works reference: BC004WH1L679M
Permit reference: BC004WH1L679M-02
Responsible organisation: Openreach
Highways authority: Worcestershire County Council
Works Type: New Service Connection
Work Category: Scheduled works
Status: Planned future work