Scheduled work by Worcestershire County Council from Saturday 25 April 2026 to Friday 18 September 2026
Marker may not indicate precise location of the roadworks.
Description: Construction of bell mouth for Mushroom Farm development.
Start: Saturday 25 April 2026 23:00
Finish: Friday 18 September 2026 22:59
Start and finish times are subject to change
Location: Allens Hill
Traffic management: No carriageway incursion
Effect on traffic: Delays unlikely
Effect on footway: None
Works reference: JZ11821439813
Permit reference: JZ11821439813-04
Responsible organisation: Worcestershire County Council
Highways authority: Worcestershire County Council
Works Type: Highway Improvement Works
Work Category: Scheduled works
Status: In progress