Scheduled work by Worcestershire County Council from Friday 23 October 2026 to Friday 30 October 2026
Marker may not indicate precise location of the roadworks.
Description: Section 278 works at temporary 184 site access to construct bell mouth and create permanent at site entrance.
Works undertaken by Shannonside Civil Eng Ltd. Emergency contact: 07345459468
Start: Friday 23 October 2026 23:00
Finish: Friday 30 October 2026 23:59
Start and finish times are subject to change
Location: Birmingham Road
Traffic management: Traffic control (two-way signals)
Effect on traffic: Delays possible
Effect on footway: None
Works reference: JZ11835086183
Permit reference: JZ11835086183-01
Responsible organisation: Worcestershire County Council
Highways authority: Worcestershire County Council
Works Type: Highway Improvement Works
Work Category: Scheduled works
Status: Planned future work