Scheduled work by Gigaclear from Saturday 29 August 2026 to Tuesday 8 September 2026
Marker may not indicate precise location of the roadworks.
Description: To re-excavate power hole due to failed power connection
Start: Saturday 29 August 2026 10:00
Finish: Tuesday 8 September 2026 22:59
Start and finish times are subject to change
Location: Cheltenham Road
Traffic management: Traffic control (give and take)
Effect on traffic: Delays likely
Effect on footway: None
Works reference: KA140WM-BURYE-CO1-02
Permit reference: KA140WM-BURYE-CO1-02-01
Responsible organisation: Gigaclear
Highways authority: Worcestershire County Council
Works Type: Utility Asset Works
Work Category: Scheduled works
Status: In progress