Scheduled work by Severn Trent Water from Monday 27 July 2026 to Thursday 30 July 2026
Marker may not indicate precise location of the roadworks.
Description: new water connection
Length of connection = 14.5m
Start: Monday 27 July 2026 07:00
Finish: Thursday 30 July 2026 17:00
Start and finish times are subject to change
Location: Evesham Road
Traffic management: Traffic control (two-way signals)
Effect on traffic: Delays possible
Effect on footway: None
Works reference: LB9225201-000006750444C
Permit reference: LB9225201-000006750444C-01
Responsible organisation: Severn Trent Water
Highways authority: Worcestershire County Council
Works Type: New Service Connection
Work Category: Scheduled works
Status: Planned future work