Scheduled work by Thames Water Utilities from Monday 2 November 2026 to Wednesday 4 November 2026
Marker may not indicate precise location of the roadworks.
Description: WATER METER INSTALLATION IN THE F/WAY
Start: Monday 2 November 2026 00:00
Finish: Wednesday 4 November 2026 23:59
Start and finish times are subject to change
Location: Ballards Close
Traffic management: Some carriageway incursion
Effect on traffic: Delays unlikely
Effect on footway: Provide Alternative Route
Works reference: MU039OMP-0375272
Permit reference: MU039OMP-0375272-01
Responsible organisation: Thames Water Utilities
Highways authority: Gloucestershire
Works Type: Utility Asset Works
Work Category: Scheduled works
Status: Planned future work